Call JA Yates Construction Ltd today on 01706 526 265
Some our of clients

Hindley Green School, Wigan

Hindley Green School just outside Wigan was a new build/refurbishment project for Eric Wright Construction to which our involvement lasted approx 12 months, the new build element backed onto the existing Primary school which had major ramifications for noise and ground water issues due to the nature of the area, our works comprised of:

Haul road reduced level dig, stone to formation and Tarmac base course

Bases and ring beam formations

Underpinning the existing structure whilst forming the bases alongside

Lift pit shutter formation and weather seal upon completion

Floor slab to ground floor

Internal and external foul and surface water drainage

Replacement of old drainage to outfall across football pitches

Formation of car parks, playgrounds.

New access pathways and disabled ramp formation

Silo bases

Temporary pumping station to minimise ground water egress into area

Land drains

Service ducts and trenches for Gas/Electricity/Water/CCTV and street lighting

Paving and flagging

Removal of haul road once works completed

Hard landscaping to all perimeter areas